GRIDCo restores Aboadze–Anwomaso power line after tree damage
GRIDCo has restored a major transmission line after tree damage disrupted electricity in Ashanti and Western regions. The repair highlights the importance of protecting Ghana’s power corridors.

Ghana’s electricity transmission network has regained a major connection following an unplanned outage that exposed the vulnerability of critical infrastructure to activities along power corridors.
The Ghana Grid Company (GRIDCo) announced that it completed repairs to the 330kV Aboadze–Anwomaso circuit at approximately 12:07pm on Thursday, 26 November 2026. The line returned to operation a day after a fallen tree damaged the infrastructure, according to the company’s restoration announcement.
What caused the interruption?
In its 25 November statement, GRIDCo attributed the fault to unauthorised tree felling by chainsaw operators. Electricity transmission was interrupted in areas of Ashanti and Western regions, and operators reduced supply to parts of Kumasi while the connection was unavailable.
The company has subsequently urged the public to avoid activities that threaten electricity infrastructure.
Why protecting transmission corridors matters
Electricity reliability depends on more than the amount of power generated. Transmission lines carry electricity between major points in the network, while distribution infrastructure delivers it to individual consumers. Damage to a transmission connection can therefore have consequences far beyond the immediate location of the fault.
For households and businesses, unexpected interruptions can affect refrigeration, communications and productive working hours. The wider economic cost of this particular incident has not been established in the statements reviewed by Nukunya.
Restoration is not the same as an end to every outage
The repaired circuit is distinct from the 161kV Anwomaso–Ahodwo upgrade covered in Nukunya’s earlier reporting on planned electricity interruptions in Kumasi. The restoration should not be interpreted as confirmation that those separate infrastructure works have finished, or that every distribution-level fault has been resolved.
Consumers experiencing continued interruptions should consult current notices from the Electricity Company of Ghana. The incident also underlines the value of preventive corridor maintenance, public awareness and coordination between infrastructure operators and local authorities.