Kumasi Power Outages: GRIDCo Gives November Work Window and December Feeder Target

GRIDCo and ECG plan targeted Kumasi power interruptions through 29 November as transmission work continues. See the workday hours, December feeder target and verified capacity figures.

Follow Nukunya
Get the latest breaking news and updates from Nukunya.

Kumasi residents face targeted daytime electricity interruptions through November as GRIDCo and ECG complete a major transmission upgrade. The 161kV line is expected to be finished by the end of November, while a fifth feeder is targeted for December. Here is what the official timetable and capacity figures mean for households and businesses.

KUMASI — Electricity infrastructure works in Greater Kumasi have entered a critical phase, with Ghana Grid Company Limited (GRIDCo) and the Electricity Company of Ghana (ECG) warning of temporary, localised power cuts as engineers upgrade the 161-kilovolt Anwomaso–Ahodwo transmission line. A separate fifth feeder at the Ridge Substation is expected by the end of December.

Officials say the investments are intended to relieve overloaded equipment and improve reliability in the Ashanti Region. The improvements are projected rather than demonstrated: construction and commissioning must be completed before consumers can assess whether interruptions become less frequent.

Kumasi Power Outages: GRIDCo Gives November Work Window and December Feeder Target Nukunya
NUKUNYA | GHANA ENERGY DATA

Kumasi Power Upgrade & Outage Tracker

Explore planned interruptions, reported electricity capacity and the two project deadlines.

Data snapshot: 4 November 2026
Potential outage hours9am–5pmAffected workdays only
Line upgrade progress70%As of 29 October
Demand above rating25.1 MVACalculated difference
Target line capacity1,000 MWNot yet verified as operational

Check the planned work period

Select a date to see whether it falls within the announced weekday work window. This is not an address-specific outage checker.

Only an official ECG area-by-area notice can confirm whether a particular community is scheduled for interruption.

Two projects, two deadlines

Greater Kumasi: reported demand and capacity

Demand572.1 MVA
Installed capacity547 MVA

Calculated difference: 25.1 MVA (4.6%).

MVA measures apparent power. This comparison does not establish an equivalent MW shortfall or continuous unmet demand.

Transmission-line capacity: previous versus target

Previous rating~364 MW
Target rating1,000 MW

Planned increase: approximately 636 MW, or 2.75 times the previous rating.

This is transmission transfer capability, not new electricity generation or verified commissioning.

What residents should know

  • The announced work period runs from 30 October to 29 November 2026, excluding weekends.
  • Potential interruptions are between 9am and 5pm on affected workdays.
  • Not every neighbourhood is necessarily affected on every weekday.
  • Conductor-stringing completion and fifth-feeder completion have different targets.
  • Network upgrades cannot guarantee the elimination of all future outages.

Leave a Reply

Your email address will not be published. Required fields are marked *

Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.